Notable Point · 1:23:50-1:25:35

How a larger Type 45 order changes average cost

The Type 45 example separates development expenditure from the cost of additional ships.

Notes

Small production runs spread development costs across fewer ships. Six Type 45s account for a £6 billion programme in this calculation. Another six are estimated at roughly £1.8 billion to £2.4 billion, giving a possible £8.4 billion programme and £700 million average for twelve ships. The estimate for fourteen is about £9 billion. These are counterfactual estimates. Once development is paid for, later expenditure concentrates on hulls and equipment. Inflation still matters, but a larger order can reduce the average programme cost assigned to each ship.