Notable Point · 43:49-45:29

Test infrastructure, class size, and readiness

The economics of the Type 45 test program show why one-time facilities, planned class size, and a navy's tolerance for delayed ships shape the trial strategy.

Notes

Shore integration facilities are expensive program assets that support multiple ships. The Type 45 program was planned around twelve hulls, and the quoted £6 billion program cost included these facilities. Describing the result as billion-pound destroyers obscures infrastructure that can be reused for successive ships and later upgrades. A large navy may accept testing more equipment aboard successive ships because a delay to one or two hulls is easier to absorb. A small navy has fewer substitutes, so it has a stronger reason to complete extensive land testing and deliver each ship ready to operate from the start.