What does early submarine steel cutting say about the reactor?

A reactor-timing question distinguishes material orders from assembly and preserves the uncertainty in the remembered lead time.

Question

Could the early steel-cutting milestone refer to reactor components that must be prepared first?

Short answer

Some components begin early, but a material-order date does not establish reactor assembly, and the lead-time estimate is explicitly approximate.

Notes

Early steel work can include material for components that will be needed much later. It does not mean that the reactor is already undergoing final assembly. A roughly four-year lead before installation is recalled for reactor work, with an explicit warning that the estimate is from memory. Ordering material, making components, and assembling them are separate stages when interpreting a construction date.