Was Dreadnought's early steel cutting preparation for assembly, or an attempt to slow the programme and keep work ticking over?
Short answerIt reflects Britain's distributed fabrication system: suppliers prepare components and sections before they arrive at Barrow for final assembly.
NotesCutting and rolling steel can begin well before submarine sections reach Barrow-in-Furness for assembly. Specialist suppliers elsewhere, including Sheffield, shape and weld substantial sections before delivery. Factory-style fabrication can make this arrangement efficient, provided the workforce can operate its systems and computers. Reactor work also begins ahead of installation, with a roughly four-year interval offered from memory and explicitly qualified. Early material orders therefore do not establish that a complete reactor or submarine was already being assembled at that date.